RO system design: from feed water to array

Design is not permeate flow divided by membrane area. What decides whether a system runs for years is four things: the flux you allow, the way you array the elements, the saturation on the concentrate side, and the pressure margin.

Applies to brackish water, surface water, wastewater reuse and seawater desalination
RO process diagram: raw water, pretreatment, cartridge filter, chemical dosing, high-pressure pump, RO array, permeate and concentrate
Single-pass RO process. Pretreatment and dosing determine how long the membranes last, the high-pressure pump provides net driving pressure, and the array decides how permeate and concentrate are split. Post-treatment and cleaning are omitted.

1. Describe the feed water first

The first input to an RO design is not a model number — it is a complete water analysis. It must include cations (Ca²⁺, Mg²⁺, Na⁺, K⁺, Ba²⁺, Sr²⁺), anions (HCO₃⁻, SO₄²⁻, Cl⁻, NO₃⁻, F⁻), SiO₂, CO₂, pH, temperature and TDS, plus turbidity, SDI₁₅, free chlorine, iron and manganese, and COD/TOC.

Three of these are routinely left out and each one changes the design:

2. Fix recovery, then area

Recovery R = Qp / Qf × 100%; concentrate flow Qc = Qf − Qp. Once recovery is fixed, the concentration factor CF = 1 / (1 − R) is fixed too: 75% recovery means 4× concentration, 80% means 5×. Concentrate salinity, osmotic pressure and scaling risk all scale with that factor.

Area comes from the design flux: A_total = Qp / J. For 100 m³/h of permeate at 17 LMH you need about 5880 m² of membrane; at 37 m² per element (400 ft²) that is roughly 159 elements, and after rounding to vessels you would typically install 160–180.

3. Choosing design flux

Design flux is empirical: it depends on the feed type and how good the pretreatment is. Commonly used ranges for 8040 elements at an annual average water temperature of 20–25 °C:

Feed typeAverage flux (LMH)Average flux (GFD)Notes
RO permeate / clean groundwater20–2612–15Low fouling load, upper end acceptable
Tap water / well water (SDI < 3)17–2210–13Most common range
Surface water (SDI 3–5)14–188–11Strengthen pretreatment
Municipal wastewater reuse12–177–10Fouling-resistant elements recommended
Industrial wastewater / high COD10–146–8UF plus activated carbon upstream
Seawater (first pass)12–177–10High pressure, low recovery

Average flux is only one constraint. You must also check the lead-element flux (normally no more than 1.3× the average, and never above the manufacturer's ceiling) and the minimum concentrate flow at the tail (usually not below 2.5–3.5 m³/h per 8040 element, higher for seawater and heavy fouling duty).

4. Array and number of passes

Single-pass systems commonly use 6 elements per vessel in a 2:1, 3:2 or 4:2 array. The array is really a way of distributing membrane area while keeping tail concentrate flow and cross-flow velocity acceptable:

Once the array is set, recalculate flux, concentrate flow and pressure drop per stage. More stages mean more interstage piping, more booster pumps and more pressure loss — more is not automatically better.

Single-pass two-stage 2:1 RO array: two pressure vessels in the first stage, one in the second, six elements per vessel
Two-stage 2:1 array: permeate from both stages is combined for post-treatment, concentrate leaves from the second stage. The tail elements sit in the highest concentration, which is where pressure drop and fouling start.

5. Pressure, pressure drop and energy

Net driving pressure NDP = P_feed − ΔP/2 − P_permeate − π_avg, where π is the average osmotic pressure across the membrane. Osmotic pressure can be estimated as about 0.85 bar per 1000 mg/L for pure NaCl at 25 °C, and commonly 0.7 bar per 1000 mg/L for natural multi-ion water; the accurate value should come from the ion composition.

On pressure drop: a single 8040 element is usually limited to 0.9–1.0 bar, and a whole stage losing much more means blocked channels or excessive flow. High-pressure pump power P = Qf × ΔP / (36 × η) with Qf in m³/h, ΔP in bar, P in kW and η the pump efficiency.

The order for cutting energy is: reduce the recovery requirement, then pick low-energy elements, then consider energy recovery (seawater), and only then look at pump efficiency — the first two usually matter far more than the pump.

6. Concentrate-side checks

Concentrate saturation is the hard constraint on system life. Check it stage by stage:

7. Pre-delivery checklist

  1. Complete water analysis, with cation/anion equivalent balance within 5%
  2. Recovery, concentration factor and concentrate disposal route all defined
  3. Average flux, lead-element flux and tail concentrate flow all within limits
  4. Low-temperature case (e.g. 10 °C or the local minimum monthly temperature) still meets the permeate flow requirement
  5. Concentrate LSI / SiO₂ / sulfate saturation acceptable, with antiscalant type and dose specified
  6. Free chlorine, ORP, temperature and pH interlocks and alarm setpoints defined
  7. High-pressure pump head includes 10–15% ageing margin, interstage boosting accounted for
  8. Per-element and per-stage pressure drop within limits
Recommendation: fill this checklist into the calculation report item by item instead of attaching only a permeate-flow-versus-pressure table. What a reviewer can follow is what has actually been delivered.
Note: this page is an independent technical compilation of public information; it is not affiliated with, authorised by or acting as an agent for any membrane manufacturer. Trademarks and model names belong to their respective owners. Parameters, series and software features may change between vendor versions; for formal design, tendering and procurement rely on the latest datasheets, official software and contractual terms. Nothing here constitutes a selection commitment or warranty.

Finish the design in your browser

733 elements from 8 manufacturers built in, with same-condition comparison, project import and report export (Excel / PDF / Word).

Sign in See features